Project Completion Update: Medium-Sized Tank Installation at Upton upon Severn

Project Description

Project Completion Update: Medium-Sized Tank Installation at Upton upon Severn

Jones Site Services & Installations is pleased to announce the successful completion of our latest project in Upton upon Severn, where our team has been on-site delivering a full installation package for two medium-sized storage tanks, complete with pipework connection and full reinstatement.

This project is a great example of our end-to-end capability—managing everything from ground preparation through to final handover. Below is an overview of the works carried out.

📍 Project Overview

The scope of works included:

  • Installation of 2 medium-sized tanks
    Our team completed the full placement, levelling, and secure installation of both units, ensuring compliance with all manufacturer and industry standards.
  • Pipework Installation
    We supplied and installed all associated pipework, connecting the new tanks to the existing system. All pipelines were pressure-tested and quality-checked prior to sign-off.
  • FRC Excavations
    All Formed Reinforced Concrete (FRC) excavations were carried out by our in-house team. This included excavation to required depth, shuttering, reinforcement placement, and concrete pouring.
  • Reinstatement Works
    Once installation and testing were complete, we reinstated all excavated areas to leave the site clean, level, and ready for use. This included backfilling, compaction, surface restoration, and final tidy.

âś” A Smooth & Successful Delivery

This project highlights the efficiency and reliability our clients can expect from Jones Site Services & Installations. By handling every element—from civil works to mechanical installation—we ensure consistent quality and complete peace of mind.

We’d like to thank our team for their continued hard work and our client in Upton upon Severn for trusting us with this installation.

If you have a similar project or would like to discuss how we can support your next installation, feel free to get in touch.

 

Project Info

Location
Upton upon Severn
Year Completed:
2025